14. Juni 2018

Sub-contractors and Project Insurance: guidance from the courts

Haberdashers’ Aske’s Federation Trust Ltd & Ors v Lakehouse Contracts Ltd & Ors [2018] EWHC 558 (TCC)

In a move that will concern sub-contractors, Fraser J at the Technology and Construction Court (TCC) found that a sub-contractor cannot rely on project insurance where the sub-contract specifically requires them to maintain separate insurance.

Facts

Lakehouse Contracts Ltd (the "Contractor") was employed by the Claimants to carry out extensive works to a school in London. The Contractor sub-contracted the roofing works for the project to Cambridge Polymer Roofing ("CPR").

The overall works were covered by project insurance which purported to cover the Contractor and any sub-contractors. In addition, the sub-contract specifically required CPR to maintain its own insurance cover to the sum of £5 million.

CPR were carrying out hot works on the roof when a fire broke out, causing extensive damage to the buildings.

The project insurers paid a settlement of £8.75 million to the Claimants to cover the damage and the issue then became whether the project insurers could claim a contribution of £5 million from CPR. CPR argued that they were co-insured under the policy and the project insurers could not pursue a subrogated claim against them.

Decision

Fraser J found that the project insurers could pursue a claim against CPR.

Where the sub-contractor had expressly agreed in the sub-contract to maintain its own insurance cover, they could not rely on the project insurance. Part of the logic behind this was that the project insurance protected a specified group, including sub-contractors, but the group had to be joined. The insurers accepted that those sub-contractors hired prior to the insurance policy being taken out were automatically within the defined group covered under the policy and that sub-contractors appointed after the policy was taken out were implied to have joined the defined group on execution of the sub-contract. The problem for CPR was that, by expressly agreeing in its sub-contract to maintain £5 million cover separately, they had never joined the 'defined group' of subcontractors to whom cover was extended.

To the extent that CPR were covered by their £5 million insurance policy, they could not rely on the project insurance.

Comment

This case may come as a surprise to many sub-contractors. This decision confirms that it is the underlying contract between the contractor and sub-contractor and the parties' intentions that will determine how the insurance provisions are interpreted. Sub-contractors would be well advised to read the terms of their sub-contracts carefully and not to assume that a project insurance policy will provide protection.

This decision is likely to lead to sub-contractors pushing back on insurance provisions in order to avoid any insurance obligations which could conflict with any overarching project insurance.

As project insurance is being increasingly used, this case will be seen as a major issue for sub-contractors and therefore be forced up the chain to become of concern to contractors. It is possible that this could damage the trust in project insurance policies moving forward, no longer being seen as the catch all policy they were intended to be.

Back to contents page

Call To Action Arrow Image

Newsletter-Anmeldung

Wählen Sie aus unserem Angebot Ihre Interessen aus!

Jetzt abonnieren
Jetzt abonnieren

Related Insights

Steuerrecht

UK REIT Horizon Scanner Q1 2024

16. Januar 2024

von mehreren Autoren

Klicken Sie hier für Details
Steuerrecht

UK REIT Horizon Scanner 2023 Q4

19. Oktober 2023

von mehreren Autoren

Klicken Sie hier für Details
Immobilien

Enforcement powers under the Building Safety Act

31. Juli 2023

von Rebecca May und Rona Westgate

Klicken Sie hier für Details