26 March 2025
Publication series – 33 of 32 Insights
When operating electricity and gas grids, German law distinguishes between (unregulated) customer systems (Section 3 No. 24a and b EnWG) and (partially or fully) regulated electricity and gas grids. The operation of a customer system is significantly less costly than grid operation and is also economically more attractive.
According to Section 3 No. 16 EnWG, customer systems are not part of the energy supply grid and the operators of such systems are accordingly exempt from the grid operator obligations. In contrast, regulatory requirements apply to grid operation, grid fees must be calculated and charged (along with grid-related levies and charges) and grid operation requires authorisation from the energy supervisory authority.
The subject of the dispute was the connection of two residential areas with 96 and 160 residential units respectively and CHP plants connected to them, as so-called customer plants, to the local electricity grid.
In its ruling of 28 November 2024 (preliminary ruling procedure), the CJEU ruled that there is no model in European law for the customer installation provision created in Germany in accordance with Section 3 No. 24a EnWG. The German regulation is therefore contrary to European law because it provides for additional exemptions from the obligations of a network operator over and above those provided for by the Internal Electricity Market Directive.
The Federal Court of Justice is expected to rule in May 2025 and there will be virtually no room for argument following the CJEU judgement (no grandfathering for old cases). It seems rather unlikely that Section 3 No. 24a EnWG will even be retroactively declared to be contrary to European law (and thus grid fees, levies and charges will have to be charged retroactively).
Many companies are likely to be affected, especially those that have previously relied on decentralised energy solutions. This can include:
In all these cases, it is questionable whether the customer system is still compliant and the following steps are therefore typically required:
26 March 2025
11 December 2024
28 November 2024
by Dr. Christian Ertel, Dr. Markus Böhme, LL.M. (Nottingham)
11 November 2024
by Multiple authors
18 July 2024
by Dr. Patrick Vincent Zurheide, LL.M. (Aberdeen), Dr. Julia Wulff
11 July 2024
by Multiple authors
27 May 2024
Power Play: Renewable Energy Update
26 January 2024
Power Play: Renewable Energy Update
16 August 2023
Power Play: Renewable Energy Update
12 July 2021
Power Play: Renewable Energy Update
23 March 2021
Power Play: Renewable Energy Update
6 April 2021
Power Play: Renewable Energy Update
25 May 2021
Power Play: Renewable Energy Update
8 June 2021
Power Play: Renewable Energy Update
18 August 2021
Power Play: Renewable Energy Update
21 September 2021
by Olav Nemling
Power Play: Renewable Energy Update
2 December 2021
Power Play: Renewable Energy Update
11 January 2022
Power Play: Renewable Energy Update
14 February 2022
Power Play: Renewable Energy Update
15 March 2022
Power Play: Renewable Energy Update
27 April 2022
Power Play: Renewable Energy Update
5 May 2022
Power Play: Renewable Energy Update
12 July 2022
by Dr. Paul Voigt, Lic. en Derecho, CIPP/E, Dr. Markus Böhme, LL.M. (Nottingham)
Power Play: Renewable Energy Update
12 April 2023
by Multiple authors
Power Play: Renewable Energy Update
6 July 2023
Power Play: Renewable Energy Update
1 September 2023
by Dr. Paul Voigt, Lic. en Derecho, CIPP/E, Alexander Schmalenberger, LL.B.
Power Play: Renewable Energy Update
3 November 2023
by Dr. Christian Ertel and Dr. Markus Böhme, LL.M. (Nottingham)
by multiple authors