2025年3月26日
Publication series – 33 / 32 观点
When operating electricity and gas grids, German law distinguishes between (unregulated) customer systems (Section 3 No. 24a and b EnWG) and (partially or fully) regulated electricity and gas grids. The operation of a customer system is significantly less costly than grid operation and is also economically more attractive.
According to Section 3 No. 16 EnWG, customer systems are not part of the energy supply grid and the operators of such systems are accordingly exempt from the grid operator obligations. In contrast, regulatory requirements apply to grid operation, grid fees must be calculated and charged (along with grid-related levies and charges) and grid operation requires authorisation from the energy supervisory authority.
The subject of the dispute was the connection of two residential areas with 96 and 160 residential units respectively and CHP plants connected to them, as so-called customer plants, to the local electricity grid.
In its ruling of 28 November 2024 (preliminary ruling procedure), the CJEU ruled that there is no model in European law for the customer installation provision created in Germany in accordance with Section 3 No. 24a EnWG. The German regulation is therefore contrary to European law because it provides for additional exemptions from the obligations of a network operator over and above those provided for by the Internal Electricity Market Directive.
The Federal Court of Justice is expected to rule in May 2025 and there will be virtually no room for argument following the CJEU judgement (no grandfathering for old cases). It seems rather unlikely that Section 3 No. 24a EnWG will even be retroactively declared to be contrary to European law (and thus grid fees, levies and charges will have to be charged retroactively).
Many companies are likely to be affected, especially those that have previously relied on decentralised energy solutions. This can include:
In all these cases, it is questionable whether the customer system is still compliant and the following steps are therefore typically required:
Power Play: Renewable Energy Update
2023年8月16日
Power Play: Renewable Energy Update
2021年5月25日
Power Play: Renewable Energy Update
2021年6月8日
Power Play: Renewable Energy Update
2021年9月21日
作者 Olav Nemling
Power Play: Renewable Energy Update
2022年1月11日
Power Play: Renewable Energy Update
2022年2月14日
Power Play: Renewable Energy Update
2022年5月5日
Power Play: Renewable Energy Update
2022年7月12日
作者 Dr. Paul Voigt, Lic. en Derecho, CIPP/E, Dr. Markus Böhme, LL.M. (Nottingham)
Power Play: Renewable Energy Update
2023年4月12日
作者 作者
Power Play: Renewable Energy Update
2023年7月6日
Power Play: Renewable Energy Update
2023年9月1日
作者 Dr. Paul Voigt, Lic. en Derecho, CIPP/E, Alexander Schmalenberger, LL.B.
Power Play: Renewable Energy Update
2023年11月3日
作者 Dr. Christian Ertel 以及 Dr. Markus Böhme, LL.M. (Nottingham)
作者