作者

Rona Westgate

Senior Knowledge Lawyer

Read More
作者

Rona Westgate

Senior Knowledge Lawyer

Read More

2020年9月28日

Under Construction - Q3 2020 – 3 / 5 观点

When is consent unreasonably withheld?

A recent decision of the Commercial Court, Apache North Sea Limited v INEOS FPS Limited [2020] EWHC 2081 (Comm), provided guidance on the scope of a party’s ability to withhold its consent under a contract where there is a provision that such consent will not be unreasonably withheld. The case confirmed that it would be unreasonable to set onerous conditions prior to giving consent particularly when the consenting party may secure a financial advantage.

Application to construction contracts

Whilst the Apache case concerned an amendment to the shipment schedule in a transportation and processing agreement, construction contracts, like many commercial agreements, often contain consent clauses, providing for consent to be secured before a contractual party is permitted to do something. These provisions then go on to provide that consent should not be unreasonably withheld. For example, the JCT 2016 suite of contracts, at clause 1.10, provides that if consent is required, such consent shall not be unreasonably held or delayed.

The Apache case provides a useful reminder as to how such clauses are likely to be interpreted.

The whole contract

In the Apache case, the court referred Lord Briggs JSC view set out in Sequent Nominees Ltd v Hautford Ltd [2020], that the correct approach is to construe a consent provision on its express terms but that that exercise was not limited to looking at the terms of consent provision in isolation. The whole contract needed to be considered. However, the court should not intervene in the evaluative exercise of the consent-provider and substitute its own judgment or seek to re-write the parties’ bargain.

However, the mere fact that through the imposition of a condition, the consent-provider may acquire an entitlement to something it did not previously have does not automatically render the condition illegitimate. Imposing a condition to address a legitimate concern on the part of the consent-provider may be acceptable when it results in a benefit which is compensatory or mitigatory in nature. For example, if a party refuses consent to an assignment to a financially weak assignee, but in fact grants consent on condition that the assignee's obligations are guaranteed this is likely to be considered reasonable (Sargeant v Macepark (Whittlebury) Limited [2004]).

Summary

The case is a useful reminder of the approach to clauses which require the consent of a party to a course of action, such consent not to be unreasonably withheld. The correct approach is to construe a consent provision in the context of the contract as a whole.

本系列内容

房地产与建筑业

Building Safety: what's in the new Building Safety Bill?

2020年9月28日

作者 Rona Westgate

房地产与建筑业

When is consent unreasonably withheld?

2020年9月28日

作者 Rona Westgate

房地产与建筑业

Construction disputes and COVID-19

2020年9月28日

作者 Rebecca May, Rona Westgate

房地产与建筑业

What is meant by design life?

2020年9月28日

作者 Rona Westgate

Call To Action Arrow Image

Latest insights in your inbox

Subscribe to newsletters on topics relevant to you.

Subscribe
Subscribe

Related Insights

房地产

Enforcement powers under the Building Safety Act

2023年7月31日

作者 Rebecca May 以及 Rona Westgate

点击此处了解更多
房地产与建筑业

Combustible materials: new regulations extend ban

2022年6月10日
Quick read

作者 Rona Westgate

点击此处了解更多
房地产与建筑业

Price volatility and construction procurement

2022年5月24日
Quick read

作者 Rona Westgate

点击此处了解更多